S, T and U can complete a work in 40, 48 and 60 days respectively. They received Rs 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has com
S, T and U can complete a work in 40, 48 and 60 days respectively. They received Rs 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work alone. What is the share of S (in Rs) from total money?
1). 4000
2). 4320
3). 4500
4). 4860
1). 4000
2). 4320
3). 4500
4). 4860
This Question has 2 answers.
4860 is the correct answer as per the ssc answer key
$ S \text{ can complete the work in } 40 \text{ days } \Rightarrow \text{One day work} = \frac{1}{40} $
$ T \text{ can complete the work in } 48 \text{ days } \Rightarrow \text{One day work} = \frac{1}{48} $
$ U \text{ can complete the work in } 60 \text{ days } \Rightarrow \text{One day work} = \frac{1}{60} $
$ \text{Let total work be } 240 \text{ (LCM of 40, 48, 60)} $
$ S \text{ efficiency} = \frac{240}{40} = 6 $
$ T \text{ efficiency} = \frac{240}{48} = 5 $
$ U \text{ efficiency} = \frac{240}{60} = 4 $
$ \text{Let total work be completed in } X \text{ days} $
$ \text{T worked for } (X-2) \text{ days, U worked for } (X-5) \text{ days} $
$ \text{Total work done:} $
$ 6X + 5(X-2) + 4(X-5) = 240 $
$ 6X + 5X - 10 + 4X - 20 = 240 $
$ 15X - 30 = 240 $
$ 15X = 270 $
$ X = 18 $
$ \text{Work done by S: } 6 \times 18 = 108 $
$ \text{Total payment } = 10800 $
$ \text{Share of S} = \frac{108}{240} \times 10800 = 4860 $
$ \text{Answer: } 4860 $
$ T \text{ can complete the work in } 48 \text{ days } \Rightarrow \text{One day work} = \frac{1}{48} $
$ U \text{ can complete the work in } 60 \text{ days } \Rightarrow \text{One day work} = \frac{1}{60} $
$ \text{Let total work be } 240 \text{ (LCM of 40, 48, 60)} $
$ S \text{ efficiency} = \frac{240}{40} = 6 $
$ T \text{ efficiency} = \frac{240}{48} = 5 $
$ U \text{ efficiency} = \frac{240}{60} = 4 $
$ \text{Let total work be completed in } X \text{ days} $
$ \text{T worked for } (X-2) \text{ days, U worked for } (X-5) \text{ days} $
$ \text{Total work done:} $
$ 6X + 5(X-2) + 4(X-5) = 240 $
$ 6X + 5X - 10 + 4X - 20 = 240 $
$ 15X - 30 = 240 $
$ 15X = 270 $
$ X = 18 $
$ \text{Work done by S: } 6 \times 18 = 108 $
$ \text{Total payment } = 10800 $
$ \text{Share of S} = \frac{108}{240} \times 10800 = 4860 $
$ \text{Answer: } 4860 $
Similar Questions
- There are three taps A, B and C in a tank. They can fill the tank in 25 hrs, 20 hrs and 10 hrs respectively. At first all of them are opened simultaneously. Then after 1 hrs, tap C is closed and tap A and B are kept running. After the 4th hour, tap B is a
- Nidhi received simple interest off Rs. 1200 when invested Rs x at 6% p.a. and Rs y at 5% p.a. for 1 year. Had she invested Rs. x at 3% p.a. and Rs. y at 8% for that year, she would have received simple interest of Rs 1,260. Find the values Rs. x an y.
- Are all the four friends viz. A, B, C and D who are sitting around a circular table, facing the centre? I) B sits second to right of D. D faces the centre. C sits to immediate right of both B and D. II) A sits to immediate left to B. C is not an immedia
- A and B can complete a piece of work in 80 and 120 days respectively. They together start the work but A left after 20 days. After another 12 days C joined B and now they complete the work in 28 more days. In how many days C can complete the work, working
- Direction: Read the following information carefully and answer the questions that follow: P, V, X, A, D, I, K and UÂ set out for trip for different number of days such as 2, 8, 11, 5, 6, 4, 7 and 3, they go to the trip in the same order but the order of n