1
1
A alone can do a work in 20 days. B is 25% more efficient than A. A and B started working and worked for 4 days. If C alone completed the remaining job in 22 days. How many days C alone takes to complete the entire job?
A alone can do a work in 20 days. B is 25% more efficient than A. A and B started working and worked for 4 days. If C alone completed the remaining job in 22 days. How many days C alone takes to complete the entire job?
1). 24 days
2). 36 days
3). 12 days
4). 20 days
1). 24 days
2). 36 days
3). 12 days
4). 20 days
This Question has 1 answers.
$ A_{\text{efficiency}} = \frac{1}{20} $
$ B_{\text{efficiency}} = \frac{125}{100} \times \frac{1}{20} = \frac{5}{4} \times \frac{1}{20} = \frac{1}{16} $
$ \text{Work done by A and B in 4 days} = 4 \times \left( \frac{1}{20} + \frac{1}{16} \right) $
$ = 4 \times \left( \frac{4}{80} + \frac{5}{80} \right) = 4 \times \frac{9}{80} = \frac{36}{80} = \frac{9}{20} $
$ \text{Remaining work} = 1 - \frac{9}{20} = \frac{11}{20} $
$ C_{\text{efficiency}} = \frac{\frac{11}{20}}{22} = \frac{11}{20} \times \frac{1}{22} = \frac{11}{440} = \frac{1}{40} $
$ \text{Total days for C to complete full work} = \frac{1}{\frac{1}{40}} = 40 $
$ B_{\text{efficiency}} = \frac{125}{100} \times \frac{1}{20} = \frac{5}{4} \times \frac{1}{20} = \frac{1}{16} $
$ \text{Work done by A and B in 4 days} = 4 \times \left( \frac{1}{20} + \frac{1}{16} \right) $
$ = 4 \times \left( \frac{4}{80} + \frac{5}{80} \right) = 4 \times \frac{9}{80} = \frac{36}{80} = \frac{9}{20} $
$ \text{Remaining work} = 1 - \frac{9}{20} = \frac{11}{20} $
$ C_{\text{efficiency}} = \frac{\frac{11}{20}}{22} = \frac{11}{20} \times \frac{1}{22} = \frac{11}{440} = \frac{1}{40} $
$ \text{Total days for C to complete full work} = \frac{1}{\frac{1}{40}} = 40 $
Similar Questions
- A @ B means `A is not smaller than B? A # B means ?A is neither smaller than nor equal to B? A % B means ?A is neither smaller than nor greater than B? A $ B means ?A is not greater than B? A * B means ?A is neither greater than nor equal to B?
- A and B can complete a piece of work in 80 and 120 days respectively. They together start the work but A left after 20 days. After another 12 days C joined B and now they complete the work in 28 more days. In how many days C can complete the work, working
- S, T and U can complete a work in 40, 48 and 60 days respectively. They received Rs 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has com
- The letters A, B, C, D, E, F and G not necessarily in that order, stand for seven consecutive integers from 1 to 10, D is 3 less than A, B is the middle term. F is as much less than B as C is greater than D, G is greater than F.
- Direction: Read the following information carefully and answer the questions that follow: P, V, X, A, D, I, K and UÂ set out for trip for different number of days such as 2, 8, 11, 5, 6, 4, 7 and 3, they go to the trip in the same order but the order of n