1
1

 After working for 6 days, Ashok finds that only 1/3 rd of the work has been done. He employs Ravi who is 60% as efficient as Ashok. How many days more would Ravi take to complete the work?

 After working for 6 days, Ashok finds that only 1/3 rd of the work has been done. He employs Ravi who is 60% as efficient as Ashok. How many days more would Ravi take to complete the work?

A). 19 days

B). 10 days

C). 20 days

D). 12 days

This Question has 1 answers.

Let Ashok's work rate be $A$ (i.e., the fraction of work he completes per day).

Since Ashok completes $\frac{1}{3}$ of the work in **6 days**, his daily work rate is:
$A = \frac{1}{3} \div 6 = \frac{1}{18}$
Thus, Ashok alone can complete the entire work in **18 days**.

Now, the remaining work to be done is:
$1 - \frac{1}{3} = \frac{2}{3}$

Ravi's efficiency is **60% of Ashok's**, so his work rate is:
$R = 0.6 \times A = 0.6 \times \frac{1}{18} = \frac{1}{30}$

Now, let **x** be the number of days Ravi takes to complete the remaining $\frac{2}{3}$ of the work:
$x \times \frac{1}{30} = \frac{2}{3}$

Solving for **x**:
$x = \frac{2}{3} \times 30 = 20$

Thus, the correct answer is:

$\boxed{20}$ **days**


Add Answer / Comment

Captcha Image